Worcester Union Station

worcester union station stock

Worcester Union Station

Adding Capacity Through Innovative Design

Built in 1911, Union Station in Worcester, Massachusetts, serves as an important multimodal connection among commuter rail, passenger rail, intercity bus services and regional bus service. It services 40 weekday commuter rail trains and 18 on the weekend. Another 15 freight and passenger trains run through the station each day. But the existing platform only provides space for one train at the station at a time, which limits the capacity and operational flexibility of the Worcester/Framingham commuter rail line.

HDR was tasked by the Massachusetts Bay Transportation Authority with designing a new fully accessible high-level centre island platform including new passenger connections to the existing Union Station building and MBTA parking lot. Associated track and signal upgrades are also included, including modifications of the existing interlocking. We are providing a wide selection of professional engineering and architectural services on the $45 million project, including civil and structural engineering, permitting, signal and track design, grant preparation, construction phase services and more.

Adding Capacity with Central Platform

Passengers currently board and alight trains by an existing side platform, built in the 1990s. Only one-third of this platform accommodates high-level boarding, while the remaining two-thirds are low-level. Because of the differences in platform height, there are boarding and alighting restrictions for mobility-impaired users and the arrangement is not fully compliant with Americans with Disabilities Act or Massachusetts Architectural Access Board requirements. Mobility-impaired riders accessing the train from the MBTA-owned parking lot to the east of the station must travel the length of the low-level boarding area to board trains, approximately 800 feet along a sidewalk and pathway that are in a state of disrepair.

The current single-side platform configuration also limits the frequency of service to the station and impacts capacity elsewhere on the line.

Train at platform at Worcester Union Station

The new 820-foot centre platform is being constructed between the existing Station Track and Track No. 1. This centre platform will allow two nine-car train sets to simultaneously operate within the station and will provide accessible entry/exit to speed up boarding and disembarking. Grade-separated access to the platform will be provided at both ends via elevators and stairs.

Access to this new centre platform will be achieved in two ways. Passengers travelling through the terminal building will travel under the track in a below-grade tunnel that repurposes a former baggage storage area. East of the terminal building, passengers arriving or leaving from an associated parking area will access the new centre platform via a new pedestrian bridge crossing over the station track. A three-stop elevator will provide access to the bridge and two levels of parking.

Innovations Add Resilience, Reduce Cost and Minimize Construction Impact

HDR’s team supported MBTA in applying for and receiving a $29 million State of Good Repair grant from the Federal Railroad Administration for the project. Key to this application was the innovative approaches being used by the project team.

The new centre island platform will be constructed of fibre reinforced polymer, or FRP, rather than traditional material such as concrete, wood or steel. FRP decking is highly durable and will not degrade due to the region’s constant snow and ice treatments during winter months. This will increase passenger safety by reducing trip hazards from spalling concrete and the failure of platform-edge tactile warning that occurs over time with the freeze-thaw cycles. In addition, the choice meant an easier construction process and reduced the schedule for the project.

The project team also significantly reduced the cost and duration of work at the station by including associated work on the station as part of the platform project. The station roof structure will be waterproofed while the station track is removed for centre island platform construction. If this waterproofing work were done as a separate project, the track structure would be within a few inches of the proposed work zone. This would require additional construction phasing activities, smaller work windows and the removal and reinstallation of newly constructed track.

The design team also developed a temporary platform that minimizes impacts to passengers and expedites construction. This temporary solution avoids the need to maintain passenger boarding operations on the existing platform, which would mean construction could only occur at night or during extended weekend outages. Instead, the temporary platform, assembled to the east of the current platform, allows uninterrupted access for the contractor. This construction approach will save at least two full construction seasons. In addition, the temporary platform can be disassembled and reused for other MBTA construction projects of similar needs.

New Interlocking, New Communications

In addition to the centre island platform, the project will also construct a new crossover interlocking between Tracks 1 and 2 about 4,000 feet to the east of the station, allowing for parallel movements. HDR provided track and signal design for this effort, which includes moving the existing signal cantilever, installation of a new signal house and modifications to the PTC database.

The change in platform location also means new needs for wayfinding assistance and communication infrastructure at the station. To support the customer experience and security enhancement, new variable message signs, closed-circuit television, public announcement speakers and emergency phones will be installed.

Construction on the project is well underway, with the temporary platform in place and foundation work complete for the new center platform and elevators. The project is scheduled to be completed in winter 2023.

worcester union station stock